SoFi Stadium

SoFi Stadium

Compliance at massive scale

  • 3.1M sq ftstadium footprint
  • 100,000fan capacity
  • 40,000+inspections

The Challenge: Managing Compliance at Massive Scale

With over 3.1 million square feet and a capacity of 100,000 fans, SoFi Stadium was one of the most ambitious construction projects in the nation. Coordinating work across countless trades while ensuring 40,000+ inspections were completed on time and in compliance posed a major logistical challenge—especially with critical seismic requirements in play.

The Solution: Inertia’s Intelligent Construction Drawings (ICDs)

To meet the demand, Inertia’s ICDs provided a centralized, visual platform to initiate, track, and manage inspections. With color-coded status maps and clickable elements, teams could instantly access inspection data by location, view progress in real time, and stay aligned across contractors, jurisdictions, and trades—all without leaving the platform.

The Result: Seamless Coordination, Fewer Delays

Inertia enabled real-time visibility and coordination, helping teams avoid missed inspections and costly rework. By simplifying complex workflows and ensuring inspections were completed before additional trades began work, Inertia played a key role in delivering SoFi Stadium on schedule and setting a new standard for large-scale construction.

Satterfield & Pontikes Construction, Inc.

Satterfield & Pontikes

Bridging BIM and Procore for field efficiency

  • Hourssaved daily
  • BIM + Procorein one drawing view

The Challenge: Bridging BIM and Procore for Field Efficiency

Satterfield & Pontikes (S&P) faced two major hurdles: visualizing job status by location within Procore and making BIM data easily accessible to field teams. These issues led to delays, rework, and time-consuming coordination efforts that strained resources and disrupted workflows.

The Solution: Inertia’s Intelligent Construction Drawings (ICDs)

S&P implemented Inertia’s ICDs to connect BIM data and Procore workflows within a user-friendly 2D drawing interface. This enabled field teams to click on components like walls or ducts and instantly view relevant properties, inspection statuses, and workflows—without leaving their Procore environment.

The Result: Time Savings and Project Clarity

With Inertia, S&P saved hours daily by eliminating the need to cross-reference tools or request info from VDC teams. ICDs provided real-time, visual clarity on project status, improved collaboration, and streamlined decision-making. As a result, S&P plans to expand Inertia's use across more phases and future projects.

Lucile Packard Children’s Hospital

Lucile Packard Children’s Hospital

DPR Construction · Massive medical expansion

  • 90%inspection pass rate
  • 56,815inspection requests
  • 568users supported

The Challenge: Managing a Massive Medical Expansion

DPR Construction faced the daunting task of expanding Lucile Packard Children’s Hospital by over half a million square feet while passing more than 56,000 inspections and navigating frequent construction changes. The key challenge was finding a cost-effective solution to streamline this highly complex and time-sensitive project.

The Solution: Inertia’s Intelligent Construction Drawings

To meet these demands, DPR implemented Inertia’s Intelligent Construction Drawings (ICDs). These digital tools enabled real-time visibility, simplified inspection approvals, and ensured better collaboration by mapping and tracking every change in the project, from in-wall installations to overhead structures.

The Outcome: A Healthier Project Timeline

Thanks to Inertia’s ICDs, DPR completed the hospital expansion efficiently, achieving a 90% inspection pass rate across 56,815 requests and supporting 568 users. The technology eliminated weeks of delays, boosted transparency, and enabled a smoother closeout—ultimately delivering a major win for both the construction team and the community.